The critical path of a network represents
A. The minimum time required for completion of project
B. The maximum time required for completion of project
C. Maximum cost required for completion of project
D. Minimum cost required for completion of project
Answer: Option A
Solution(By Examveda Team)
The critical path of a network represents The minimum time required for completion of projectJoin The Discussion
Comments ( 5 )
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
B is write
B is the right answer
Pls explain
B is the correct
The Critical path of network represents longest overall duration of project