The critical path of a network represents

Answer & Solution
Correct Answer: Option A
The critical path of a network represents The minimum time required for completion of project
Examveda
Question posted by Examveda
Community

Join the Discussion

5 Comments
Ram Kumar
Ram Kumar 5 years ago
B is write
Adarsh K
Adarsh K 5 years ago
B is the right answer
RAHUL TANDON
RAHUL TANDON 6 years ago
Pls explain
Ajaj Alam
Ajaj Alam 7 years ago
B is the correct
RAVI PRAJAPATI
RAVI PRAJAPATI 7 years ago
The Critical path of network represents longest overall duration of project