The energy required per unit mass to grind limestone particles of very large size to 100 μm is 12.7 kWh/ton. An estimate (using Bond's law) of the energy to grind the particles from a very large size to 50 μrn is

Answer & Solution
Correct Answer: Option C
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

1 Comment
Kinza Hamid
Kinza Hamid 6 years ago
How??