The form work from the sides of beams can be removed only after

Answer & Solution
Correct Answer: Option A
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

1 Comment
Sajjad Shah
Sajjad Shah 6 years ago
As per IS Code it is 7 day minimum period to remove formwork from sides of beam.