The primary reason behind the success of the Jubilee Line Extension (London) in geotechnical terms was:

Answer & Solution
Correct Answer: Option B
The extension's success was attributed to the use of earth pressure balance TBMs and segmental linings for soft ground tunneling under sensitive structures.