The reduced levels of the string at the consecutive sight rails A and B are 203.575 m, 203.475 m respectively. If the difference of their R.D.s is 10 m, the gradient of the sewer line is

Answer & Solution
Correct Answer: Option C
Let's discuss the solution. Join the discussion