The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed

A. 5 m

B. 10 m

C. 15 m

D. 20 m

Answer: Option A


This Question Belongs to Civil Engineering >> Building Construction

Join The Discussion

Comments (1)

  1. Riju Chakraborty
    Riju Chakraborty:
    2 months ago

    Single-stage well point: Up to 5 m depth.
    Multi-stage well point: More than 5 m (typically up to 10–12 m or more, depending on conditions).