The start or completion of task is called
A. An event
B. An activity
C. A duration
D. None of these
Answer: Option A
Solution(By Examveda Team)
The start or completion of task is called An eventRelated Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Join The Discussion