The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as
A. Duration
B. Total float
C. Free float
D. Interfering float
Answer: Option C
Solution(By Examveda Team)
Free Float is the amount of time that an activity can be delayed without delaying the early start date of any successor activity.Related Questions on Industrial Engineering and Production Management