The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as

A. Duration

B. Total float

C. Free float

D. Interfering float

Answer: Option C

Solution(By Examveda Team)

Free Float is the amount of time that an activity can be delayed without delaying the early start date of any successor activity.