The time taken by a trained worker to perform an operation, while working a steady pace, is known as
A. Standard time
B. Normal time
C. Representative time
D. None of these
Answer: Option A
A. Standard time
B. Normal time
C. Representative time
D. None of these
Answer: Option A
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion