The time which results in the least possible direct cost of an activity is known as
A. Normal time
B. Slow time
C. Crash time
D. Standard time
Answer: Option B
Solution(By Examveda Team)
The time which results in the least possible direct cost of an activity is known as slow timeJoin The Discussion