The work study is done by means of
A. Planning chart
B. Process chart
C. Stop watch
D. Any one of these
Answer: Option C
Solution(By Examveda Team)
The main objective of work study is to improve productivity of men, machines and materials.The work study is also used in determining the standard time that a qualified worker should take to perform the operation when working at a normal place.
Dear sir but work study constist method study and work measurement. In work measurement the tool is stop watch but in method study its is process chart so how to say fundamental tool in wok study is stopwatch.