Total manufacturing time is multiplied to manufacturing cycle efficiency to calculate

A. manufacturing cycle efficiency

B. value added manufacturing time

C. responding time

D. delivery time

Answer: Option B

Solution(By Examveda Team)

Total manufacturing time is multiplied to manufacturing cycle efficiency to calculate value added manufacturing time. Value added time is the processes and activities in the production or manufacturing process that improve the product or add usefulness to it.

This Question Belongs to Management >> Management Accounting