'Value' for value engineering and analysis purposes is defined as
A. Purchase value
B. Saleable value
C. Depreciated value
D. Function/cost
Answer: Option D
Solution(By Examveda Team)
'Value' for value engineering and analysis purposes is defined as costRelated Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion