What caused delays in the Metro tunnel beneath the Hooghly River in Kolkata?

Answer & Solution
Correct Answer: Option C
The tunnel passed under the Hooghly River through water-bearing alluvial silt, leading to water ingress and requiring specialized TBMs and grouting.