What geological factor led to construction delay in the Atal Tunnel project?

Answer & Solution
Correct Answer: Option B
The fault zone with water ingress in the Seri Nallah section led to excessive inflow of water and unstable tunneling conditions, causing delays and the need for additional support systems.