What major geological factor delayed the construction of the Boston Big Dig project?

Answer & Solution
Correct Answer: Option C
The Boston Big Dig encountered significant delays due to soft clay and high groundwater levels. Extensive dewatering, ground improvement, and monitoring systems were implemented to control settlements.