What was the major geological issue in the Chunnel (Channel Tunnel) project?
Answer & Solution
Correct Answer:
Option
A
The Channel Tunnel passed through chalk marl, which presented groundwater control issues. Pressurized TBMs and sealing techniques were used to handle water ingress.