When prior to the due date of performance, the promisor absolutely refuses to perform the contract, it is known as-

A. Abandonment of contract

B. Actual breach of contract

C. Remission of contract

D. Anticipatory breach of contract

Answer: Option D


This Question Belongs to Law >> Indian Contract Act