When slack of an activity is negative
A. It represents a situation where extra resources are available and the completion of project is not delayed
B. It represents that a programme falls behind schedule and additional resources are required to complete the project in time
C. The activity is critical and any delay in its performance will delay the completion of whole project
D. All of the above
Answer: Option B
Solution(By Examveda Team)
When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in timeRelated Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion