Which hazard was encountered during excavation of the Brenner Base Tunnel?
Answer & Solution
Correct Answer:
Option
D
Swelling rock such as anhydrite was encountered. Upon contact with water, it expanded, exerting pressure on the tunnel lining. Countermeasures included reinforced linings and waterproofing.