Which of the following statement is correct?
A. When slack of an activity is zero, it falls only on critical path
B. CPM technique is useful to minimize the direct and indirect expenses
C. Critical path of a net work represents the minimum time required for completion of project
D. All of the above
Answer: Option D
Solution(By Examveda Team)
- When slack of an activity is zero, it falls only on critical path.- CPM technique is useful to minimize the direct and indirect expenses.
- Critical path of a net work represents the minimum time required for completion of project.
Join The Discussion
Comments ( 1 )
Related Questions on Industrial Engineering and Production Management
The essential condition for the decompression of an activity is that
A. The project time should change due to decompression
B. After decompression the time of an activity invariably exceeds its normal time
C. An activity could be decompressed to the maximum extent of its normal time
D. None of the above
A. CAM < DAM
B. CAM > DAM
C. CAM = DAM
D. There is no such criterion
Critical path maximum time consuming path.. 😯😯