Which of the following statement is correct?

Answer & Solution
Correct Answer: Option D
- When slack of an activity is zero, it falls only on critical path.
- CPM technique is useful to minimize the direct and indirect expenses.
- Critical path of a net work represents the minimum time required for completion of project.
Examveda
Question posted by Examveda
Community

Join the Discussion

1 Comment
Ajaj Alam
Ajaj Alam 6 years ago
Critical path maximum time consuming path.. 😯😯