Which one of the following statements is not correct for heading and benching method of tunnelling?

A. Drilling and mucking can be done simultaneously

B. Benching provides a platform for working on heading

C. Removal of muck from the heading is very easy

D. None of these

Answer: Option C


This Question Belongs to Civil Engineering >> Tunnel Engineering