Work done by A in one day is half of the work done by B in one day. Work done by B is half of the work done by C in one day. If C alone can complete the work in 7 days, in how many days can A, B and C together complete the work ?

A. 4 days

B. 14 days

C. 21 days

D. 28 days

E. None of these

Answer: Option A

Solution(By Examveda Team)

$$\eqalign{ & {\text{C's 1 day's work}} \cr & = \frac{1}{7} \cr & {\text{B's 1 day's work}} \cr & = \left( {\frac{1}{2} \times \frac{1}{7}} \right) \cr & = \frac{1}{{14}} \cr & {\text{A's 1 day's work}} \cr & = \left( {\frac{1}{2} \times \frac{1}{{14}}} \right) \cr & = \frac{1}{{28}} \cr & \left( {{\text{A}} + {\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{28}} + \frac{1}{{14}} + \frac{1}{7}} \right) \cr & = \frac{7}{{28}} \cr} $$
Hence, A, B and C together can complete the work in 4 days.

This Question Belongs to Arithmetic Ability >> Time And Work