Working efficiencies of P and Q for completing a piece of work are in the ratio 3 : 4. The number of days to be taken by them to complete the work will be in the ratio ?

Answer & Solution
Correct Answer: Option D
Since we know efficiency and time are inversely proportional to each other.

$$\eqalign{ & \,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,{\text{P}}:{\text{Q}} \cr & {\text{Efficiency }}3:4 \cr & {\text{Time }}\,\,\,\,\,\,\,\,\,\,{\text{ }}4:3 \cr} $$