X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.
A. 6 days
B. 8.1 days
C. 5.1 days
D. 7 days
E. None of these
Answer: Option C

X=1/3---4=12
Y=1/6----3=18
Z=1/2-----5=10days
1/12+1/18+1/10=43/60
Remaining 1-43/60=17/60
1/18----1days
17/60----18*17/60=5.1 days