You are asked to design sewer pipes of diameters 0.4 m to 0.9 m at maximum flow, you will assume the sewer flow running at

A. Full depth

B. Half full

C. Two third full

D. Three fourth full

Answer: Option C


This Question Belongs to Civil Engineering >> Waste Water Engineering

Join The Discussion

Comments ( 3 )

  1. Amrit Negi
    Amrit Negi :
    3 years ago

    c is correct answer

  2. Abhishek Raj
    Abhishek Raj :
    4 years ago

    It's two-third full.

    up to 0.4m - half full.

    0.4 to 0.9 - two third.

    Greater than 0.9m - three-fourth full

  3. Harendra Prajapati
    Harendra Prajapati :
    5 years ago

    It's two-third full.

    up to 0.4m - half full.

    0.4 to 0.9 - two third.

    Greater than 0.9m - three-fourth full.