A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be

Answer & Solution
Correct Answer: Option C
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

2 Comments
Hiren
Hiren 6 years ago
(6+4*15+60)/6 = 21
Muhammad Noman
Muhammad Noman 7 years ago
Minimum time=6 min
Maximum time=60 minutes
Frequent time=15 minutes
Expected time=[6+(4*15)+60]