ExamVeda
Login
Home
21
A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work ?
Discuss
Answer & Solution
Answer: Option A
Solution:
  A   :   B
Efficiency →   100% : 125%
  4 : 5
Time 5 : 4
  ×1.2↓   ↓×1.2
Actual time   6 days   $${\text{4}}\frac{4}{5}$$ days
22
A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is = ?
Discuss
Answer & Solution
Answer: Option B
Solution:
Let time taken by B and C = x days
∴ Time taken by A = 3x days
∴ Part of work done by A, B and C in 1 day
$$\eqalign{ & = \frac{1}{{\text{x}}} + \frac{1}{{3{\text{x}}}} = \frac{{3 + 1}}{{3{\text{x}}}} = \frac{4}{{3{\text{x}}}} \cr & \therefore \frac{4}{{3{\text{x}}}} = \frac{1}{{24}} \cr & \Rightarrow 3{\text{x}} = 4 \times 24 \cr & \Rightarrow {\text{x}} = \frac{{4 \times 24}}{3} = 32\,{\text{days}} \cr} $$
∴ Time taken by A = 32 × 3 = 96 days.
Alternet :
Work done by all of them together in $$\frac{1}{{24}}$$
Efficiency of A : Efficiency of (B + C) = 1 : 3
Work done by A in 1 day = $$\frac{1}{{24}}$$ × $$\frac{1}{{4}}$$ = $$\frac{1}{{96}}$$
i.e., A alone can finish the job in 96 days.
Alternet :
Suppose A can complete the job in 3x days and (B + C) can complete the job in x days.
$$\eqalign{ & \frac{{3{\text{x}} \times {\text{x}}}}{{3{\text{x}} + {\text{x}}}} = 24 \cr & \Rightarrow \frac{{3{\text{x}}}}{4} = 24 \cr & \Rightarrow {\text{x}} = 32 \cr & 3{\text{x}} = 96\,{\text{days.}} \cr} $$
23
Five men are working to complete a work in 15 days. After five days 10 women are accompanied by them to complete the work in next 5 days. If the work is to be done by women only, then in how many days could the work be over if 10 women have started it ?
Discuss
Answer & Solution
Answer: Option C
Solution:
5 men's 15 day's work = 5 men's 10 day's work + 10 women's 5 day's work
⇒ 5 men's 5 day's work = 5 women's 5 day's work
⇒ 10 women's 5 day's work
$$\eqalign{ & = \left( {\frac{1}{{15}} \times 5} \right) \cr & = \frac{1}{3} \cr} $$
⇒ 10 women's 1 day's work = $$\frac{1}{{15}}$$
∴ 10 women can complete the work in 15 days.
24
A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?
Discuss
Answer & Solution
Answer: Option A
Solution:
100 men's 40 day's work + 100 men's 5 day's work = 1
⇒ 100 men's 45 day's work = 1
So, if the contractor had not engaged additional men, 100 men would have finished the work in 45 days.
Difference in time = (45 - 40) = 5 days
25
A man, a woman and a boy can do a piece of work in 6, 9 and 18 days respectively. How many boys must assist one man and one woman to do the work in 1 day ?
Discuss
Answer & Solution
Answer: Option D
Solution:
(1 man + 1 woman)'s 1 day's work
$$\eqalign{ & = \frac{1}{6} + \frac{1}{9} \cr & = \frac{5}{{18}} \cr & {\text{Remaining work}} \cr & = \left( {1 - \frac{5}{{18}}} \right) \cr & = \frac{{13}}{{18}} \cr} $$
Work done by 1 boy in 1 day = $$\frac{1}{{18}}$$
$$\eqalign{ & \therefore {\text{Number of boys required}} \cr & = \left( {\frac{{13}}{{18}} \times 18} \right) \cr & = 13 \cr} $$
26
A man is twice as fast as a women and a woman is twice as fast as a boy in doing a work. If all of them, a man , a woman and a boy can finish the work in 7 days, a boy will do it alone ?
Discuss
Answer & Solution
Answer: Option A
Solution:
  Man  :  Woman  :  Boy
Efficiency   4 : 2 : 1

Total work = Time × (Efficiency of man + woman + boy)
⇒ 7 days × (4 + 2 + 1) = 49 units
∴ Boy can do this work in = $$\frac{{49}}{1}$$ = 49 days
27
A's 2 days work is equal to B's 3 days work. If A can complete the work in 8 days, then to complete the work B will take ?
Discuss
Answer & Solution
Answer: Option B
Solution:
$$\eqalign{ & {\text{According to the question,}} \cr & \Rightarrow 2{\text{A}} = {\text{3B}} \cr & \Rightarrow \frac{{\text{A}}}{{\text{B}}} = \frac{3}{2} \cr & \Rightarrow {\text{Then efficiency ratio }} \cr & {\text{A}}:{\text{B}} = 3:2 \cr} $$
⇒ We know that time is inversely proportional to efficiency
⇒ Then time taken by them in ratio
$$\eqalign{ & {\text{A}}:{\text{B}} = \mathop {\mathop {{\text{ }}2}\limits_{4 \times \downarrow } {\text{ }}}\limits_{8{\text{days}}} :\mathop {\mathop 3\limits_{{\text{ }} \downarrow \times 4} }\limits_{12{\text{days}}} \cr & \because {\text{A can do the work in 8 days}} \cr & \Rightarrow {\text{i}}{\text{.e, 2 units}} \to {\text{8}} \cr & \,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,{\text{1 unit}} \to {\text{4}} \cr & \Rightarrow {\text{Time taken by B}} \to {\text{3 units}} \cr & = 3 \times 4 \cr & = 12{\text{ days}} \cr} $$
28
If A, B and C can complete a piece of work in 6 days. If A can work twice faster than B and thrice faster then C, than the number of days C alone can complete the work is ?
Discuss
Answer & Solution
Answer: Option B
Solution:
A + B + C = 6 days [6 days total work]
$$\eqalign{ & {\text{According to the question,}} \cr & {\text{Ratio of their efficiencies,}} \cr & {\text{A}}:{\text{B}}:{\text{C}} \cr & 6{\text{ }}:3{\text{ }}:2 \cr & {\text{Total efficiencies}} \cr & \left( {6 + 3 + 2} \right){\text{units}} = 11{\text{ units}} \cr & {\text{Total work}} = 11 \times 6 = 66{\text{ units}} \cr} $$
Therefore, time taken by C to complete the work
$$\frac{{{\text{Total work}}}}{{{\text{Efficiencies}}}} = \frac{{66}}{2} = 33{\text{ days}}$$
29
A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?
Discuss
Answer & Solution
Answer: Option A
Solution:
A : B = 1 : 2
B : C = 1 : 2 (Multiply by 2)
B : C = 2 : 4
A : B : C = 1 : 2 : 4
30
If 3 men or 9 boys can finish a piece of work in 21 days, in how many days can 5 men and 6 boys together do the same piece of work ?
Discuss
Answer & Solution
Answer: Option E
Solution:
$$\eqalign{ & {\text{1 men's 1 day's work}} \cr & = \frac{1}{{21 \times 3}} \cr & = \frac{1}{{63}} \cr & {\text{1 boy's 1 day's work}} \cr & = \frac{1}{{21 \times 9}} \cr & = \frac{1}{{189}} \cr & \left( {{\text{5 men}} + {\text{6 boy}}} \right){\text{'s 1 day's work}} \cr & = \frac{5}{{63}} + \frac{6}{{189}} \cr & = \frac{5}{{63}} + \frac{2}{{63}} \cr & = \frac{7}{{63}} \cr & = \frac{1}{9} \cr} $$
Hence, 5 men's and 6 boy's together can do the work in 9 days.