ExamVeda
Login
Home
Construction Planning and Management
?

Assertion (A): Activity 57 is critical.
Reason (R): Earliest finish time and latest finish time for events 57 are same

Answer & Solution
Correct Answer: Option A
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

1 Comment
Mahesh Pawar
Mahesh Pawar 2 years ago
Critical Activity: In project scheduling, a critical activity is an activity that has no slack time. Slack time is the amount of time an activity can be delayed without delaying the entire project. If the earliest finish time and the latest finish time of an activity are the same, it means there is no slack time for that activity, making it critical.
Therefore, both Assertion (A) and Reason (R) are correct, and Reason (R) is the correct explanation for Assertion (A).