Due to change in price level, a revised estimate is prepared if the sanctioned estimate exceeds
A. 2.0 %
B. 2.5 %
C. 4.0 %
D. 5.0 %
Answer: Option D
Related Questions on Estimating and Costing
A. Mid-section formula
B. Trapezoidal formula
C. Prismoidal formula
D. All the above
Size, capacity and materials need be specified for
A. Bib-cocks
B. Stop-cocks
C. Ball valves
D. All the above
The expected out turn of 12 mm plastering with cement mortar is
A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m
A. Excavation
B. Surface dressing
C. Cutting
D. Surface excavation