Examveda
Examveda

Economic saving of time results by crashing

A. Cheapest critical activity

B. Cheapest noncritical activity

C. Costliest critical activity

D. Costliest noncritical activity

Answer: Option A


Join The Discussion

Related Questions on Construction Planning and Management

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{2}$$

B. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{3}$$

C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{4}$$

D. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{5}$$

E. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$