In testing a pile by load test, pile platform is loaded with one and half times the design load and a maximum settlement is noted. The load is gradually removed and the consequent rebound is measured. For a safe pile, the net settlement (i.e. total settlement minus rebound) per tonne of test load should not exceed

A. 10 mm

B. 15 mm

C. 20 mm

D. 25 mm

Answer: Option D


This Question Belongs to Civil Engineering >> RCC Structures Design

Join The Discussion

Related Questions on RCC Structures Design

If the shear stress in a R.C.C. beam is

A. Equal or less than 5 kg/cm2, no shear reinforcement is provided

B. Greater than 4 kg/cm2, but less than 20 kg/cm2, shear reinforcement is provided

C. Greater than 20 kg/cm2, the size of the section is changed

D. All the above