Match the following
| List-I (Element of production) | List-II (Elements) |
| a. Control of Due dates | 1. Cribes |
| b. Control of Material | 2. EOQ |
| c. Control of Quality | 3. SQC |
| d. Control of Tooling | 4. Scheduling |
A. a-1, b-2, c-3, d-4
B. a-4, b-3, c-2, d-1
C. a-1, b-3, c-4, d-2
D. a-1, b-3, c-2, d-4
Answer: Option D