Match the following.
| List-I (Element of Production) | List-II (Elements) |
| a. Control of due dates | 1. Cribes |
| b. Control of material | 2. SQC |
| c. Control of quality | 3. EOQ |
| d. Control of tooling | 4. Scheduling |
A. a-1, b-2, c-3, d-4
B. a-4, b-3, c-2, d-1
C. a-1, b-3, c-4, d-2
D. a-1, b-3, c-2, d-4
Answer: Option A