Match the following
| List-I (Elements of Production Control) | List-II (Elements) |
| a. Control of Due Dates | 1. Planned Schedules |
| b. Control of Quality | 2. Inspection |
| c. Control of Tooling | 3. Cribs |
| d. Control of Materials | 4. EOQ |
A. a-1, b-2, c-3, d-4
B. a-3, b-4, c-2, d-1
C. a-3, b-1, c-2, d-4
D. a-1, b-4, c-3, d-2
Answer: Option A