Pick up the correct statement from the following with regards to C.P.M. network analysis of projects
A. The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
B. The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
C. Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
D. All the above
Answer: Option D
The normal time required for the completion of project in the above problem is
A. 9 days
B. 13 days
C. 14 days
D. 19 days
A. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{2}$$
B. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{3}$$
C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{4}$$
D. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{5}$$
E. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$
A construction schedule is prepared after collecting
A. Number of operations
B. Output of labour
C. Output of machinery
D. All the above
A. 3.5 and $$\frac{5}{6}$$
B. 5 and $$\frac{{25}}{{36}}$$
C. 3.5 and $$\frac{{25}}{{36}}$$
D. 4 and $$\frac{5}{6}$$