The constraints in case of resource smoothening operation would be

A. Resources

B. Project duration time

C. Both resources and project duration time

D. None of the above

Answer: Option B


Join The Discussion

Related Questions on Construction Planning and Management

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{2}$$

B. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{3}$$

C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{4}$$

D. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{5}$$

E. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$