The following statements' relate to project network. Choose the correct answer for the statements being correct or-incorrect.
Statement I An activity cannot be represented by more than one arrow, but. an arrow can represent one or more activities.
Statement II The activities in a critical path can be preponed or postponed.

Answer & Solution
Correct Answer: Option B
Let's discuss the solution. Join the discussion