The following statements' relate to project network. Choose the correct answer for the statements being correct or-incorrect.
Statement I An activity cannot be represented by more than one arrow, but. an arrow can represent one or more activities.
Statement II The activities in a critical path can be preponed or postponed.

A. Both statements are correct

B. Both statements are incorrect

C. Statement II is correct, but Statement I is incorrect

D. Statement I is correct, but Statement II is incorrect

Answer: Option B