Whenever an activity has zero total float, then
A. Free float of the activity must be zero but independent float need not be zero
B. Independent float must be zero but free float need not be zero
C. Free float and independent float both must be zero
D. Free float and independent float both need not be zero
Answer: Option C
The normal time required for the completion of project in the above problem is
A. 9 days
B. 13 days
C. 14 days
D. 19 days
A. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{2}$$
B. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{3}$$
C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{4}$$
D. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{5}$$
E. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$
A construction schedule is prepared after collecting
A. Number of operations
B. Output of labour
C. Output of machinery
D. All the above
A. 3.5 and $$\frac{5}{6}$$
B. 5 and $$\frac{{25}}{{36}}$$
C. 3.5 and $$\frac{{25}}{{36}}$$
D. 4 and $$\frac{5}{6}$$