While solving an assignment problem, an activity is assigned to a resource through a square with zero opportunity cost because the objective is to?

A. Minimize total cost of assignment

B. Reduce the cost of assignment to zero

C. Reduce the cost of that particular assignment to zero

D. All of the above

Answer: Option A

Solution(By Examveda Team)

While solving an assignment problem, an activity is assigned to a resource through a square with zero opportunity cost because the objective is to minimize total cost of assignment. The objective of assignment problem is to assign a number of jobs to an equal number of machines so as to minimize the total assignment cost or to minimize the total consumed time for execution of all the jobs. In the multi-objective assignment problem, the objectives alone are considered as fuzzy.

This Question Belongs to Management >> Operations Research

Join The Discussion

Related Questions on Operations Research

The use of decision models.

A. Is possible when the variables value is known

B. Reduces the scope of judgement & intuition known with certainty in decision-making

C. Require the use of computer software

D. None of the above