ExamVeda
Login
Home
11
Time and progress chart of a construction, is also known as
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board
12
The difference between the time avail-to do a job and the time required to do the job, is known as
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
13
The Overall in-charge of an organization at the site responsible for the execution of the works, is
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
14
For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
Discuss
Answer & Solution
Answer: Option D
Solution:
This is the correct answer. In construction project management using a bar chart (Gantt chart), each activity is represented by a horizontal bar. The activities mentioned in the question include:

1. Supply of materials for concrete
2. Formwork, reinforcing, and placing of concrete
3. Removal of formwork
4. Curing of concrete
Each of these activities requires a separate bar on the chart.
15
Various activities of a project, are shown on bar charts by
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
16
The main disadvantage of line organization, is
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board
17
The main principle of an organization, is
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board
18
A critical ratio scheduling
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board
19
A golden rule for the procurement of construction stones, suggests
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
20
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board