51
Railway projects are treated as
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
52
If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is
Discuss
Answer & Solution
Answer: Option A
No explanation is given for this question. Let's Discuss on Board
53
Construction team means
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board
54
Assertion (A): Activity 57 is critical.
Reason (R): Earliest finish time and latest finish time for events 57 are same
Discuss
Answer & Solution
Answer: Option A
No explanation is given for this question. Let's Discuss on Board
55
The time which results in the least possible construction cost of an activity, is known as
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
56
The area under the Beta distribution curve is divided into two equal parts by
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board
57
The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
58
Which one of the following is not an excavating and moving type of equipment?
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board