11
The probability distribution of activity times in PERT follows following distribution
Discuss
Answer & Solution
Answer: Option C
Solution:
The PERT distribution produces a bell-shaped curve that is nearly normal. It is essentially a Beta Distribution that has been extended to the maximum and minimum and given strict definitions for the mean and variance
12
The probability distribution of project completion in PERT follows following distribution
Discuss
Answer & Solution
Answer: Option D
Solution:
Gaussian distribution is a bell-shaped curve, and it is assumed that during any measurement values will follow a normal distribution with an equal number of measurements above and below the mean value.
13
If a worker gets a daily wage of Rs. HA, then according to Rowan plan, his maximum daily earnings can be
Discuss
Answer & Solution
Answer: Option A
Solution:
If a worker gets a daily wage of Rs. HA, then according to Rowan plan, his maximum daily earnings can be 2 HA.
14
In order to avoid excessive multiplication of facilities, the layout preferred is
Discuss
Answer & Solution
Answer: Option B
Solution:
process layout is a design for the floor plan of a plant which aims to improve efficiency by arranging equipment according to its function.
The production line should ideally be designed to eliminate waste in material flows, inventory handling and management.