1
Time study is
Discuss
Answer & Solution
Answer: Option A
Solution:
Time study is a structured process of directly observing and measuring human work using a timing device to establish the time required for completion of the work by a qualified worker when working at a defined level of performance
2
The chart which gives an estimate about the amount of materials handling between various work stations is known as
Discuss
Answer & Solution
Answer: Option C
Solution:
A Travel Chart is a simple table that is useful where there are multiple (and possibly irregular) movement between places. It is a variation on the Check Sheet, indicating movements from and to any combination of a given set of locations.
3
One of the basic essentials of an incentive plan is that
Discuss
Answer & Solution
Answer: Option D
Solution:
One of the basic essentials of an incentive plan is that All standards should be based on time studies
4
Standard time as compared to normal time is
Discuss
Answer & Solution
Answer: Option A
Solution:
Standard time is always greater compared to normal time
5
The correct sequence of phases in value engineering is
Discuss
Answer & Solution
Answer: Option A
Solution:
The correct sequence of phases in value engineering is Creative phase, information phase, investigation phase, evaluation phase
6
The reasons which are basically responsible for the formation of a queue should be that
Discuss
Answer & Solution
Answer: Option D
Solution:
The reasons which are basically responsible for the formation of a queue should be that.
- The average service rate Hess than the average arrival rate
- Output rate is linearly proportional to input
- Output rate is constant and the input varies in a random manner
7
For ship vessel industry the following layout is best suited
Discuss
Answer & Solution
Answer: Option C
Solution:
In a fixed position layout, personnel, supplies and equipment are brought to the site where the product will be assembled, rather than the product being moved through an assembly line or set of assembly stations.
Other fixed position layout examples include construction shipbuilding, aircraft, aerospace, farming, drilling for oil, home repair and automated car washes.
8
Breakeven analysis is a
Discuss
Answer & Solution
Answer: Option A
Solution:
Break-even analysis is a technique widely used by production management and management accountants. .
Total variable and fixed costs are compared with sales revenue in order to determine the level of sales volume, sales value or production at which the business makes neither a profit nor a loss (the "break-even point").
9
The deductions for, employees provident fund start
Discuss
Answer & Solution
Answer: Option D
Solution:
The deductions for employees provident fund start after 240 days of joining the service
10
PERT/CPM, techniques can be used for following applications
Discuss
Answer & Solution
Answer: Option D
Solution:
CPM is a statistical technique of project management in which planning, scheduling, organising, coordination and control of well-defined activities take place. PERT is a technique of planning and control of time.