Actual performance of a task is called
Discuss
Answer & Solution
Answer: Option A
Solution:
In the context of industrial engineering and production management, the actual performance of a task is referred to as an "event." An event represents a specific occurrence or action related to the task or process being monitored or analyzed. It is a significant happening within the context of the task's execution.

The other options do not accurately describe the actual performance of a task:
Option B: An activity typically refers to a broader set of tasks or actions and may include multiple events.
Option C: A duration refers to the amount of time it takes to complete a task but does not capture the specific performance itself.
Option D: None of these is incorrect as "event" is the appropriate term for the actual performance of a task.

So, the correct answer is Option A: An event, which best represents the actual performance of a task in this context.

2
The essential condition for the decompression of an activity is that
Discuss
Answer & Solution
Answer: Option C
Solution:
The essential condition for the decompression of an activity is that An activity could be decompressed to the maximum extent of its normal time
3
According to MAPI formula, the old machine should be replaced by new one when
(Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum)
Discuss
Answer & Solution
Answer: Option A
Solution:
According to MAPI formula, the old machine should be replaced by new one when
(Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum)
CAM < DAM
4
Bar charts are suitable for
Discuss
Answer & Solution
Answer: Option A
Solution:
Bar charts are suitable for Minor works
5
The simplex method is the basic method for
Discuss
Answer & Solution
Answer: Option C
Solution:
The simplex method is the basic method for Linear programming.
The Simplex method is a search procedure that sifts through the set of basic feasible solutions, one at a time, until the optimal basic feasible solution is identified.
6
'O' on a PERT/CPM chart represents
Discuss
Answer & Solution
Answer: Option A
Solution:
The Symbol on a PERT / CPM chart represents:
An ordinary event
A significant event representing some mile-stone
An event to be transferred to other network chart
Dangling event
7
The most popular type of organisation used for Civil Engineering Constructions is
Discuss
Answer & Solution
Answer: Option A
Solution:
Line organization is the most oldest and simplest method of administrative organization. According to this type of organization, the authority flows from top to bottom in a concern.
The line of command is carried out from top to bottom.
8
In break even analysis, total cost consists of
Discuss
Answer & Solution
Answer: Option C
Solution:
The break-even point (BEP) or break-even level represents the sales amount—in either unit (quantity) or revenue (sales) terms—that is required to cover total costs, consisting of both fixed and variable costs to the company.
Total profit at the break-even point is zero.
9
In break-even analysis, total cost consists of
Discuss
Answer & Solution
Answer: Option C
Solution:
The break-even point (BEP) or break-even level represents the sales amount—in either unit (quantity) or revenue (sales) terms—that is required to cover total costs, consisting of both fixed and variable costs to the company.
Total profit at the break-even point is zero.
10
The work study is done by means of
Discuss
Answer & Solution
Answer: Option D
Solution:
Work study is a systematic technique to analyze work processes and improve efficiency and productivity.

It comprises two major components: Method Study and Work Measurement.

Method Study aims at improving the method of performing a task. For this, tools like the process chart are used to visualize and analyze the steps involved in the current method.

Work Measurement is used to determine the time taken to perform a task. A stop watch is commonly used in time studies to record the duration of different job elements.

A planning chart is more associated with project planning and scheduling but may still be involved in the broader context of work study, especially during implementation phases.

Therefore, since all these tools may be used in different contexts of work study, the correct answer is: Any one of these.