ExamVeda
Login
Home
91
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only $${\frac{5}{8}}$$ th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?
Discuss
Answer & Solution
Answer: Option A
Solution:
$$\eqalign{ & {\text{From, }} \cr & \frac{{{{\text{m}}_1} \times {{\text{d}}_1} \times {{\text{t}}_1}}}{{{{\text{w}}_1}}} = \frac{{{{\text{m}}_2} \times {{\text{d}}_2} \times {{\text{t}}_2}}}{{{{\text{w}}_2}}} \cr & {\text{Let extra workers be x}} \cr & \Rightarrow \frac{{20 \times 12}}{{\frac{5}{8}}} = \frac{{\left( {20 + x} \right) \times 4}}{{\frac{3}{8}}} \cr & \Rightarrow 4 \times 12 = \frac{{\left( {20 + x} \right) \times 4}}{3} \cr & \Rightarrow 36 = 20 + x \cr & \Rightarrow x = 16 \cr & \Rightarrow {\text{Extra workers }} = {\text{16}} \cr} $$
92
A alone can complete a piece of work in 18 days and B alone in 15 days, B alone worked at it for 10 days and then left the work. In how many more days, will A alone complete the remaining work ?
Discuss
Answer & Solution
Answer: Option C
Solution:
$$\eqalign{ & {\text{B's}}\,{\text{10}}\,{\text{day's}}\,{\text{work}} \cr & = \left( {\frac{1}{{15}} \times 10} \right) = \frac{2}{3} \cr & {\text{Remaining}}\,{\text{work}} \cr & = \left( {1 - \frac{2}{3}} \right) = \frac{1}{3} \cr & {\text{Now}},\frac{1}{{18}}{\text{work}}\,{\text{is}}\,{\text{done}}\,{\text{by}}\,{\text{A}}\,{\text{in}}\,{\text{1}}\,{\text{day}} \cr & \therefore \frac{1}{3}\,{\text{work}}\,{\text{is}}\,{\text{done}}\,{\text{by}}\,{\text{A}}\,{\text{in}} \cr & \left( {18 \times \frac{1}{3}} \right) = 6\,{\text{days}} \cr} $$
93
A can do a piece of work in 12 days. When he had worked for 3 days. B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work ?
Discuss
Answer & Solution
Answer: Option A
Solution:
Total work = 12
Efficiency 1 units/day = 12 days time (A)
After 3 days A finishes 3 units.
∴ Work left =12 - 3 = 9 units
9 units of work, 3 units/day = 3 days (A + B)
(A + B)'s one day work = 3 units
A's one day work = 1 unit
B's one day work = 3 - 1 = 2 units
∴ B completes whole work in
$$\eqalign{ & = \frac{{{\text{Total work}}}}{{{\text{Efficiency}}}} \cr & = \frac{{12}}{2} \cr & = {\text{6 days }} \cr} $$
94
45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?
Discuss
Answer & Solution
Answer: Option C
Solution:
According to the question,
Let the remaining work is complete in D days
$${\text{4}}{{\text{5}}_{{\text{men}}}} \times {\text{1}}{{\text{6}}_{{\text{days}}}}$$    = $$\left( {{\text{4}}{{\text{5}}_{{\text{men}}}} \times {{\text{4}}_{{\text{days}}}}} \right)$$    + $${\left( {{\text{45}} + {\text{36}}} \right)_{{\text{men}}}}$$   $$ \times {\text{D}}$$
$$\eqalign{ & \Rightarrow \frac{{540}}{{81}} = {\text{D}} \cr & \Rightarrow {\text{D}} = 6\frac{2}{3}{\text{ days}} \cr} $$
95
A started a ,work and left after working for 2 days. Then B was called and he finished the work in 9 days. had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone, finish the whole work ?
Discuss
Answer & Solution
Answer: Option C
Solution:
Suppose A takes x days to finish the work alone and B take y days to finish the work alone.
$$\eqalign{ & {\text{Then,}}\frac{2}{x} + \frac{9}{y} = 1.....(i) \cr & {\text{And,}}\frac{3}{x} + \frac{6}{y} = 1 \cr & \Leftrightarrow \frac{1}{x} + \frac{2}{y} = \frac{1}{3} \cr & \Leftrightarrow \frac{2}{x} + \frac{4}{y} = \frac{2}{3}.....({\text{ii)}} \cr & {\text{Subtracting (ii) from (i), }} \cr & {\text{We get}}:\frac{5}{y} = \frac{1}{3}{\text{or }}y = 15 \cr & {\text{Putting }}y = 15{\text{ in (i), }} \cr & {\text{We get}}:\frac{2}{x} = \frac{2}{5}{\text{or }}x = 5 \cr} $$
Hence, A alone takes 5 days while B alone takes 15 days to finish the work.
96
Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the if she worked alone ? Assume that Sudha is more efficient than Asha.
Discuss
Answer & Solution
Answer: Option C
Solution:
Suppose, Asha takes x days to complete the task alone
while Sudha takes y days to complete it alone
Since Sudha is more efficient than Asha, we have x > y
$$\eqalign{ & {\text{Asha's 1 day's work}} = \frac{1}{x} \cr & {\text{Sudha's 1 day's work}} = \frac{1}{y} \cr & \left( {{\text{Asha}} + {\text{Sudha}}} \right){\text{'s 1 day's work}} \cr & = \frac{1}{x} + \frac{1}{y} \cr & = \frac{{x + y}}{{xy}} \cr} $$
If Asha and Sudha each does half of the work alone, time taken
$$\eqalign{ & = \left( {\frac{x}{2} + \frac{y}{2}} \right){\text{ days }} \cr & = \left( {\frac{{x + y}}{2}} \right){\text{ days}}{\text{.}} \cr & \therefore \frac{{x + y}}{2} = 45 \cr & \Rightarrow x + y = 90 \cr & {\text{From (i) and (ii), }} \cr & {\text{We have}}:\frac{{xy}}{{20}} = 90{\text{ or }}xy = 1800 \cr & {\text{Now, }}xy = 1800{\text{ and }}x + y = 90 \cr & \Rightarrow x = 60,{\text{ }}y = 30{\text{ }}\left[ {\because x > y} \right]{\text{ }} \cr} $$
Hence, Asha alone will take 60 days to complete the task.
97
A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?
Discuss
Answer & Solution
Answer: Option C
Solution:
$$\eqalign{ & {\text{B's 3 day's work}} \cr & = \left( {\frac{1}{{21}} \times 3} \right) \cr & = \frac{1}{7} \cr & {\text{Remaining work}} \cr & = \left( {1 - \frac{1}{7}} \right) \cr & = \frac{6}{7} \cr & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{14}} + \frac{1}{{21}}} \right) \cr & = \frac{5}{{42}} \cr} $$
Now, $$\frac{5}{{42}}$$ work is done by A and B in 1 day
$$\eqalign{ & \therefore \frac{6}{7}{\text{ work is done by A and B in}} \cr & = \left( {\frac{{42}}{5} \times \frac{6}{7}} \right) \cr & {\text{ = }}\frac{{36}}{5}{\text{ days}} \cr & {\text{Hence, total time taken}} \cr & = \left( {3 + \frac{{36}}{5}} \right){\text{days}} \cr & = 10\frac{1}{5}{\text{days}}{\text{.}} \cr} $$
98
A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?
Discuss
Answer & Solution
Answer: Option D
Solution:
L.C.M. of total days = 24
One day work of A + B = $$\frac{{24}}{8}$$ = 3 units/day
One day work of B = $$\frac{{24}}{12}$$ = 2 units/day
One day work of C = $$\frac{{24}}{12}$$ = 2 units/day
A and B work for 4 days they completed
$$\eqalign{ & = 3 \times 4 \cr & = 12{\text{ units}} \cr & \therefore {\text{Work left}} \cr & = 24 - 12 \cr & = {\text{12 units}} \cr & {\text{B's 2 days work}} \cr & = 2 \times 2 \cr & = {\text{4 units}} \cr & \therefore {\text{Work left}} \cr & = 12 - 4 \cr & = {\text{8 units}} \cr & {\text{Now, }} \cr & {\text{C's complete the work in}} \cr & = \frac{8}{2} \cr & = 4{\text{ days}} \cr} $$
99
A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?
Discuss
Answer & Solution
Answer: Option A
Solution:
  (T.W.)
60
2 units/day  
  30 days
(A + B)
$$\eqalign{ & \left( {{\text{A }} + {\text{ B}}} \right){\text{ worked for 20 days}} \cr & {\text{So, they completed}} \cr & 20 \times 2 = 40{\text{ units}} \cr & {\text{Work left}} = 60 - 40 = {\text{20 units}} \cr} $$
  (T.W.)
2 0
1 units/day  
  20 days
(A)
A's efficiency 1 units/day A will complete the whole work in
$$\eqalign{ & = \frac{{{\text{Total work}}}}{{{\text{Efficiency}}}} \cr & = \frac{{60}}{1} \cr & = 60{\text{ days}} \cr & \cr & {\bf{Alternate:}} \cr & \left( {{\text{A}} + {\text{B}}} \right) \times {\text{10}} = {\text{A}} \times {\text{20}} \cr & \frac{{{\text{A + B}}}}{{\text{A}}} = \frac{2}{1} \cr & {\text{Total work}} \cr & = 2 \times 30 \cr & = {\text{60 units}} \cr & {\text{Time taken by A alone}} \cr & = \frac{{60}}{1} \cr & = 60{\text{ days}} \cr} $$
100
16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left and 4 women joined them. How many days will they take to complete the remaining work ?
Discuss
Answer & Solution
Answer: Option B
Solution:
$$\eqalign{ & 16{\text{ women}} \times {\text{12}} = {\text{12 men}} \times {\text{8}} \cr & {\text{2 women}} = {\text{1 man}} \cr & {\text{Total work}} \cr & = {\text{12 men}} \times {\text{8 days}} \cr & = {\text{96 units}} \cr & {\text{16 men do work in 3 days}} \cr & = 16 \times 3 \cr & = 48{\text{ units}} \cr & {\text{Work left }}96 - 48 = 48{\text{ units}} \cr} $$
16 men - 10 men left = 6 men + 4 women join
$$\eqalign{ & {\text{6men}} + {\text{2 men}} = {\text{8 men}} \cr & {\text{8 men will do 48 units in}} \cr & = \frac{{48}}{8} \cr & = 6{\text{ days}} \cr} $$