Learn Tunnel Engineering MCQ questions & answers are available for a Civil Engineering students to clear GATE exams, various technical interview, competitive examination, and another entrance exam. Tunnel Engineering MCQ question is the important chapter for a Civil Engineering and GATE students. Page-5 section-1
41
For transferring the tunnel alignment through shafts, we adopt the following steps: 1.Hanging two or more plumb lines in the shaft 2.Determining the bearing of the plumb lines i.e. plumb plane 3.Suspending a 35 kg weight by each plumb line 4.Immersing the weights of both the plumb lines in the buckets containing water The correct sequence of steps is:
What is the correct sequence of the following events in rock tunnelling?
1. Marking tunnel profile
2. Loading explosives and blasting
3. Checking misfire
4. Mucking
5. Removing foul gas
6. Setting up and drilling
7. Guniting