91
ERP system is built on a . . . . . . . . utilising a common computing platform.
A)
Centralised database
B)
Individual database
C)
Modular databases
D)
Centralised layout
Answer & Solution
Answer: Option
A
92
Which one of the following statement is not correct?
A)
Assignment model is a special case of a linear programming problem
B)
In queueing models, poisson arrivals and exponential services assumed
C)
In transportation problem, the non-square matrix is made square by adding a dummy row or a dummy column
D)
None of the above
Answer & Solution
Answer: Option
A
93
Control systems of production involves
A)
TQM
B)
schedule control policies
C)
QC
D)
all of these
Answer & Solution
Answer: Option
D
94
Assignment model is used to
A)
assign a work to the customer
B)
assign a target to the worker
C)
find out a profit
D)
assign number of jobs to available machine and people
Answer & Solution
Answer: Option
D
95
Which of the following statement is true?
A)
The design of products and services is partially dependent on the productive system design and vice-versa
B)
Process design is concerned with the overall sequences of operations required to achieve the design specification of the product
C)
Form design is concerned with the appearance and aesthetic considerations and also the size, volume and weight of the product which are secondary to the performance of the product
D)
All of the above
Answer & Solution
Answer: Option
D
96
Match the following.
List-I (Decision Variables)
List-II (Factors to be Considered)
a. Initial investment
1. Price
b. Output investment
2. Actual vs rated capacity
c. Obsolescence
3. Modification
d. Operating requirements
4. Ease of use
A)
a-1, b-2, c-4, d-3
B)
a-1, b-3, c-4, d-2
C)
a-1, b-2, c-3, d-4
D)
a-4, b-1, c-2, d-3
Answer & Solution
Answer: Option
C
97
Secondary factors of location includes
A)
soil and climate
B)
industrial environment
C)
financial aids
D)
all of these
Answer & Solution
Answer: Option
D
98
Which of the following question is not relevant in making a facility decision?
A)
Where should the capacity be located?
B)
When is the capacity needed?
C)
What kind of capacity is needed?
D)
None of the above
Answer & Solution
Answer: Option
C
99
Which of the following steps is the first step in production scheduling?
A)
Sequencing
B)
Loading
C)
Expediting
D)
Classifying
Answer & Solution
Answer: Option
B
100
Dummy activities are used in a network to
A)
facilitate computation of slacks
B)
satisfy precedence requirements
C)
determine project completion time
D)
avoid use of resources
Answer & Solution
Answer: Option
B