81
The determination of standard time in a complex job system is best done through
Discuss
Answer & Solution
Answer: Option D
Solution:
The determination of standard time in a complex job system is best done through analysis of standard data system.
82
Product layout is best suited where
Discuss
Answer & Solution
Answer: Option D
Solution:
Product layout is best suited where
- One type of product is produced
- Product is standardized
- Product is manufactured in large quantities
83
The process layout is best suited where
Discuss
Answer & Solution
Answer: Option C
Solution:
The process layout is best suited where Few number of non-standardized units is to be produced
84
The type of organisation preferred for an automobile industry, is
Discuss
Answer & Solution
Answer: Option C
Solution:
Line and Staff Organization is a compromise of line organization. It is more complex than line concern. Division of work and specialization takes place in line and staff organization. The whole organization is divided into different functional areas to which staff specialists are attached.
85
At the break-even point,
Discuss
Answer & Solution
Answer: Option C
Solution:
the break-even point refers to the revenues necessary to cover a company's total amount of fixed and variable expenses during a specified period of time.
86
The technique of value analysis can be applied to
Discuss
Answer & Solution
Answer: Option D
Solution:
The technique of value analysis can be applied to
- Complicated items only
- Simple items only
- Crash programmer items only
87
The production cost per unit can be reduced by
Discuss
Answer & Solution
Answer: Option B
Solution:
The production cost per unit can be reduced by Producing more with the same inputs
88
Gantt chart is used for
Discuss
Answer & Solution
Answer: Option C
Solution:
Frequently used in project management, a Gantt chart provides a graphical illustration of a schedule that helps to plan, coordinate, and track specific tasks in a project.
89
Routing assists engineers in deciding in advance
Discuss
Answer & Solution
Answer: Option C
Solution:
Routing assists engineers in deciding in advance the methods of proper utilization of machines.
90
The objective of time study is to determine the time required to complete a job by
Discuss
Answer & Solution
Answer: Option B
Solution:
The objective of time study is to determine the time required to complete a job by Average worker