81
Break-even analysis consists of
Discuss
Answer & Solution
Answer: Option C
Solution:
Break-even analysis consists of Fixed and variable costs
82
PERT analysis is based on
Discuss
Answer & Solution
Answer: Option D
Solution:
PERT Analysis. Program Evaluation and Review Technique (PERT) is a method used to examine the tasked that are in a schedule and determine a variation of the Critical Path Method (CPM).
It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project
83
Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
Discuss
Answer & Solution
Answer: Option C
Solution:
Dummy activity on a PERT/CPM chart means, it Consumes neither time nor resources
84
A CPM family includes
Discuss
Answer & Solution
Answer: Option D
Solution:
A CPM family includes
- CPA (Critical Path Analysis)
- CPP (Critical Path Plotted)
- CPS (Critical Path Scheduling)
85
M.T.M. is used to
Discuss
Answer & Solution
Answer: Option D
Solution:
M.T.M. is used to
- Improve existing methods
- Establish time standards
- Develop effective methods in advance of the beginning of production
86
In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if
Discuss
Answer & Solution
Answer: Option D
Solution:
In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known
87
The main objective of work measurement is to
Discuss
Answer & Solution
Answer: Option D
Solution:
The main objective of work measurement is to
- Plan and schedule of production
- Formulate a proper incentive scheme
- Estimate the selling prices and delivery dates
88
Which of the following equations is not in conformity with others?
Discuss
Answer & Solution
Answer: Option A
Solution:
- Knowledge × skill = ability
- Ability × motivation = performance
- Attitude × situation = motivation
89
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time and tn = Most likely time)
Discuss
Answer & Solution
Answer: Option D
Solution:
The probabilistic time is given by $$\frac{{{{\text{t}}_{\text{o}}} + {{\text{t}}_{\text{p}}} + 4{{\text{t}}_{\text{n}}}}}{6}$$
Where to = Optimistic time, tp = Pessimistic time and tn = Most likely time.
90
Acceptance sampling is used in
Discuss
Answer & Solution
Answer: Option C
Solution:
Acceptance sampling is used in Mass production